Inspection
Work Planning

This is some text inside of a div block
Case Study

Commissioning Inventory in 7 Days

How an alkylate production facility received their commissioning inventory in a week
Download PDF
Intelligent Drawing Platform
5
Business days
250
P&IDs processed
85%
Faster than manual
100%
Coverage accuracy
Figure 02

01The Challenge

A newly constructed alkylate production facility was ready to commission and had no commissioning inventory. The contractor had already mobilized a full team of inspectors, but there was no organized way to track tagged items against the system boundaries drawn on the P&IDs.

The manual fallback — field teams scratching IDs off drawings by hand — would have burned weeks of labor and introduced error into the one register the whole commissioning effort depended on.

The cost of waiting: three to four weeks of delay with inspectors already on site and on the clock.

02The Approach

1

Drawing processing

250 AutoCAD P&IDs were loaded into IDP, which identified the existing symbology and associated labels across the full drawing set.

Output: digitized drawing set
2

Targeted extraction

IDP's hierarchy tool selected every tagged element and grouped it by commissioning system — equipment, instrumentation, piping, relief devices, and specialty items.

Output: system-grouped inventory
3

Deliverable assembly

The hierarchy was exported and post-processed into a system-based commissioning register, formatted for immediate field use.

Output: field-ready register

03What Changed

Zero mobilization delay

Inspectors already on site began field verification on schedule instead of waiting on paperwork.

Complete coverage

Every tagged element captured from the drawings, rather than whatever manual review happened to catch.

System-aligned tracking

The register mirrors the commissioning system boundaries the team actually works to.

Reusable asset data

The same extracted structure carries forward into operations and maintenance.

04By the Numbers

MetricManualAutomatedImprovement
Timeline3–4 weeks5 days85% faster
Labor hours480+4092% reduction
Coverage70–80%100%Complete
P&IDs processed250250Same scope
Next Step
Mechanical integrity is entering a new era. See what this approach returns at your facility.
MI Program Assessment